SERVICES
1. SECURING CERTIFICATE OF ZONING CERTIFICATION
Zoning Certification is a pre-requisite for the land titling and establishment commercial buildings.
REQUIREMENTS
- Vicinity Map
- Certificate of Land Title (If not an owner an affidavit of consent is required)
- Tax Declaration
- Tax Clearance
- Sketch Plan with technical description
FEES
Zoning Certification Fee ….. P 500.00/lot
| Follow these steps |
It will take |
Please approach |
1. Submission of Requirements The client asks the requirements the from the MPDC staff
MPDC staff interviews the client , explains how to fill up the application form and give the list of requirements |
10 minutes |
ENGR. MIGUEL BULAC , JR Project Development Officer |
2. Review and Verification
The Clients comes back and give the requirements
MPDC staff reviews and verifies the documents |
10 minutes |
ENGR. MIGUEL BULAC , JR Project Development Officer |
3. Preparation of the certification
The clients waits for the Zoning certification
MPDC staff prepares the certification. |
15 minutes |
ENGR. MIGUEL BULAC , JR Project Development Officer |
4. Issuance of Certificate
Applicant receives the Certificate of Zoning Classification. |
5 minutes |
MA. MERCEDES E. SALINAS MPDC |
2. SECURING ZONING/LOCATIONAL CLEARANCE FOR BUILDING PERMIT
All Enterprises and private persons constructing a new building or applying for expansion/renovation are required to secure a zoning clearance upon application for building permit.
This should be done before the start of construction to ensure that the building/business is allowed in the chosen location as per the Municipal Comprehensive Land Use Plan (CLUP).
REQUIREMENTS (in 2 copies)
- Application form for Zoning Clearance, duly notarized
- Certificate of title/deed of sale/affidavit of consent
- Tax declaration
- Tax clearance (latest)
- Affidavit of ownership if untitled lot, duly notarized
- Highway clearance from the DPWH Office (if within 15m. distance from the centerline of the nat’l road)
- Barangay certification from the Office of the Barangay Captain
- Bill of materials and estimates ( conformed by the owner)
- Complete set of plans signed and sealed by Architect/Civil Engineer
- Environmental Clearance Certificate (ECC) or Certificate of Non- Coverage (CNC) (when applicable)
- Vicinity Map
- Brown envelope
- If lot is not owned:
- Contract of lease - Authorization to occupy the lot
FEES
|
TYPE OF STRUCTURE/PROJECT COST
|
CLEARANCE FEE
|
|
1. ZONING/LOCATIONAL CLEARANCE
|
|
|
A.) Single Residential Structure Attached or Detached
|
|
|
1.) P 100,000.00 and below
|
P 200.00
|
|
2.) Over P 100,000 to P 200,000
|
P 400.00
|
|
3.) Over P 200,000
|
500+1/10 of 1% in excess of P 200,000.00
|
|
B) Apartments/Townhouses
|
|
|
1.) P 500,000 and below
|
P 1,000.00
|
|
2.) Over P 500,000 and to P 2 million
|
P 1,500.00
|
|
3.) Over P 2 million
|
P 2,500.00+1/10 of 1% of cost in excess of P 2 million regardless of the numbers of doors
|
|
C.) Dormitories
|
|
|
1.) P 2 million and below
|
P 2,500.00
|
|
2.) Over P 2 million
|
2,500.00+1/10 of 1% of cost in excess of P 2 million regardless of the number of doors
|
|
D.) Institutional
|
|
|
PROJECT COST OF WHICH IS:
|
|
|
1.) Below P 2 million
|
P 2,000.00
|
|
2.) Over P 2 million
|
2,000+1/10 of 1% of cost in excess of P 2 million
|
|
E.) Commercial, Industrial and Agro-Industrial Project
|
|
|
cost of which is
|
|
|
1.) Below P 100,000
|
P 1,000.00
|
|
2.) Over P 100,000-P 500,000
|
P 1,500.00
|
|
3.) Over P 500,000- P 1 million
|
P 2,000.00
|
|
4.) Over P 1 million-P 2 million
|
P 3,000.00
|
|
5.) Over P 2 million
|
P 5,000.00+1/10 of 1% of cost in excess of P2 million
|
|
F.) Special Uses/Special Projects
|
|
|
(GASOLINE STATION, CELL SITES, SLAUGHTER HOUSE, TEATMENT PLAN ETC.)
|
|
|
1.) Below P 2 million
|
P 5,000.00
|
|
2.) Over P 2 milion
|
P 5,000.00+1/10 of 15 of cost in excess of P 2 million
|
|
G.) Alteration/Expansion ( Affected areas/cost only)
|
Same as original application
|
HOW TO AVAIL THE SERVICE
| Follow these steps |
It will take |
Please approach |
|
1. Submission of requirements
The client asks the requirements the from the MPDC staff
MPDC staff interviews the client , explains how to fill up the application form and give the list of
|
10 minutes |
ENGR. MIGUEL BULAC , JR Project Development Officer |
2. Review/verify/determine zoning fees
The Clients comes back and give the requirements
MPDC staff reviews , verifies the documents and determines the zoning fees |
10 minutes |
ENGR. MIGUEL BULAC , JR Project Development Officer |
3. Payment of fees
Clients pays the required fees to the Treasurer’s office |
10 minutes |
BEDA LEGASPI Revenue Collection Clerk II
RUFA ACUÑA Revenue Collection Clerk II |
4. Preparation of Locational Clearance
Client waits for the Zoning/ locational clearance
MPDC Staff prepares, processes and records Locational Clearance. |
30 minutes |
ENGR. MIGUEL BULAC , JR Project Development Officer |
5. Approval of Locational Clearance
Clients waits for the approval of the zoning/locational clearance
MPDC/Zoning administrator approves the zoning clearance |
3 minutes |
MA. MERCEDES E. SALINAS Municipal Zoning Administrator Officer |
6. Notification
MPDC Staff submit to the Office of the Mayor for notification
Client receives the zoning /locational clearance |
3 minutes |
LUCIANO A. BONGALOS Municipal Mayor |
|